Update on Preston Youth Zone Operator
The Cabinet approved a report on 10 August 2017, recommending the commencement of a procurement exercise to secure a Youth Zone Operator for the delivery of the Preston Youth Zone. A Prior Information Notice was issued on 12 October 2017 to prepare the market for the release of the tender documents.
In June 2016 the Cabinet received a report which provided a cost estimate of £6.925m for the design and construction of the Preston Youth Zone. The county council has committed a capital contribution of £5.925m to the scheme with the requirement that the Youth Zone operator provide the remaining £1m.
The estimate of £6.925m has been reviewed to take account of a recalculation of Tender Price Inflation, a revised design to accommodate the co-location of the Preston Youth Offending Team service and an enhanced specification of the external cladding. This has resulted in an increase in the cost estimate of £1.605m and a total capital cost of £8.53m.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 12/04/2018
Anticipated restriction: Part I -
Decision due: 12 Apr 2018 by Cabinet
Lead member: Cabinet Member for Children, Young People and Schools, Leader of the County Council
Contact: Sue Procter Email: Sue.Procter@lancashire.gov.uk Tel: 01254 770985.
Decisions
- 12/04/2018 - Update on Preston Youth Zone Operator
Agenda items
- 12/04/2018 - Cabinet Update on Preston Youth Zone Operator 12/04/2018