This report sets out a recommendation to amend the basis upon which the Cuerden Development Site – Earthworks procurement exercise will be undertaken. This report includes a revised estimated contract value of £3.8m, following the identification of additional works required as part of this procurement exercise since the original report was approved by Cabinet on 18 January 2018. The report provides detail on the additional works value identified for this project.
This is deemed to be a Key Decision and the provisions of Standing Order No.26 have been complied with.
Decision type: Key
Reason Key: Expenditure > £1,500,000;
Decision status: Recommendations Approved
Notice of proposed decision first published: 05/04/2018
Anticipated restriction: Part I -
Decision due: 12 Apr 2018 by Cabinet
Lead member: Leader of the County Council
Contact: Paul Johnstone Email: paul.johnstone@lancashire.gov.uk Tel: 01772 535465.