Decision Maker: Director of Strategic & Integrated Commissioning
Decision status: Recommendations Approved
Is Key decision?: No
The peer advocacy contract was agreed to be
extended from 30 days to 59 days to give slightly more evaluation
time due to some last-minute changes in documentation as time
scales are extremely tight. This would result in a longer
mobilisation period, the current 30 day extension would have been a
tight turnaround for the providers, this decision will mitigate a
situation where there is a gap in service delivery.
Nichola Morris, Commissioning Manager, took the decision to approve the increase from a 30-day extension to a 59-day extension.
Divisions Affected: N/A;
Contact: Kashif Ahmed Email: kashif.ahmed@lancashire.gov.uk.