Decision Maker: Director of Highways and Transport
Decision status: Recommendations Approved
Is Key decision?: No
The DfT retaining walls programme was established in 2019 to cover repairs to retaining walls on priority routes in the East of the County. The programme has been in progress since with most projects now complete.
There is one remaining high priority project in progress for which funding is in place for completion.
There are two low priority projects outstanding where the scope has been reduced and funding can be made available to support other projects within the programme. These are:
There are three completed projects that currently have an overspend and require additional funding to reconcile the budgets and allow the projects to be closed out financially. These are:
It is proposed to transfer £55,000 of available funds from the two low priority projects to cover the overspends on the three overspent projects as follows:
There is no change to the overall programme budget, all the projects are in the same programme year and the total of all the changes for this programme are less than £100,000.
Head of service is asked to approve the transfer in order to financially reconcile the programme.
Ridwan Musa, Head of Service Highways Operations and Design, on behalf of the Matt Townsend, Director of Highways and Transport took a decision to make changes to project budgets within the Bridges Maintenance - DfT Retaining Walls Programme in order to financially reconcile the programme.
Divisions Affected: Chorley Rural East; Mid Rossendale; Rossendale South;
Contact: Ridwan Musa Email: ridwan.musa@lancashire.gov.uk.
Date of decision: 02/09/2024