Decision Maker: Director of Highways and Transport
Decision status: Recommendations Approved
Is Key decision?: No
In Aug 2021 the funding was transferred to
SLGC as the work was to be completed as part of that programme. The
amount transferred was £751,778.50 but during its time in the
Programme only design work was incurred at a cost of £41,088.
It has now been agreed that the work will return to the original
Safer Roads scheme for completion of the project and the remaining
grant funding of £710,690.50 will be transferred back to the
Transport Programme.
John Davies, Head of Highways Network Management, on behalf of Matt Townsend, Director of Highways and Transport, took a decision to approve the transfer of the grant funding of £710,690.50 back to the Transport Programme.
Divisions Affected: Lancaster Central; Lancaster South East;
Contact: John Davies Email: john.davies2@lancashire.gov.uk.
Date of decision: 04/09/2024
Accompanying Documents: