Accrington Woodhaven Day Centre - Boiler Replacement

Decision Maker: Director of Finance and Commerce

Decision status: Recommendations Approved

Is Key decision?: No

Purpose:

A decision to approve and conduct a mini-competition procurement exercise from the Reactive and Planned Improvement Works Framework (Lot 6) at Accrington Woodhaven Day Centre - Boiler Replacement.

Decision:

Sarah Robinson, Head of Service, Property took the decision which has been delegated to her in accordance with the Council's Directorate Schemes of Delegation for the approval of the commencement of a mini-competition procurement process to publish a mini competition from Reactive and Planned Improvement Works (Lot 6) at Woodhaven Day Centre, Accrington – Boiler Replacement. 

Divisions Affected: Accrington North;

Contact: Sarah Robinson Email: sarah.robinson@lancashire.gov.uk.

Date of decision: 04/03/2025

Accompanying Documents: