Decision Maker: Director of Highways and Transport
Decision status: Recommendations Approved
Is Key decision?: No
A number of 2024/25 P2 Drainage Defect schemes
have overspent and have outstanding costs, while others have
remining funds. As the end of the 2024/25 financial year approaches
these budgets are required to balance the individual budgets within
the scope of the overall programme, with the view of the projects
been financial closed after year end.
Transfer from PPMS ID 15825 24/25 Burnley P2 Drainage Defects
Transfer £15,000 to PPMS ID 15830 24/25 Lancaster P2 Drainage
Defects
£15,000 to PPMS ID 15826 24/25 Pendle P2 Drainage
Defects
£10,000 to PPMS ID 15829 24/25 Ribble Valley P2 Drainage
Defects
Total £40,000
Transfer from PPMS ID 15827 24/25 Hyndburn P2 Drainage
Defects
Transfer £5,000 to PPMS ID 15829 24/25 Ribble Valley P2
Drainage Defects
£15,000 to PPMS ID 15828 24/25 Rossendale P2 Drainage
Defects
Total £20,000
John Davies, Head of Highways Network Management, on behalf of Matt Townsend, Director of Highways and Transport took a decision to approve the transfers as set out in the report.
Divisions Affected: (All Divisions);
Contact: John Davies Email: john.davies2@lancashire.gov.uk.
Date of decision: 31/03/2025
Accompanying Documents: