Balance of 2024/25 Drainage Defect Budgets P2

Decision Maker: Director of Highways and Transport

Decision status: Recommendations Approved

Is Key decision?: No

Purpose:

A number of 2024/25 P2 Drainage Defect schemes have overspent and have outstanding costs, while others have remining funds. As the end of the 2024/25 financial year approaches these budgets are required to balance the individual budgets within the scope of the overall programme, with the view of the projects been financial closed after year end.

Transfer from PPMS ID 15825 24/25 Burnley P2 Drainage Defects
Transfer £15,000 to PPMS ID 15830 24/25 Lancaster P2 Drainage Defects
£15,000 to PPMS ID 15826 24/25 Pendle P2 Drainage Defects
£10,000 to PPMS ID 15829 24/25 Ribble Valley P2 Drainage Defects
Total £40,000

Transfer from PPMS ID 15827 24/25 Hyndburn P2 Drainage Defects
Transfer £5,000 to PPMS ID 15829 24/25 Ribble Valley P2 Drainage Defects
£15,000 to PPMS ID 15828 24/25 Rossendale P2 Drainage Defects
Total £20,000

Decision:

John Davies, Head of Highways Network Management, on behalf of Matt Townsend, Director of Highways and Transport took a decision to approve the transfers as set out in the report.

 

Divisions Affected: (All Divisions);

Contact: John Davies Email: john.davies2@lancashire.gov.uk.

Date of decision: 31/03/2025

Accompanying Documents: