Decision Maker: Director of Highways and Transport
Decision status: Recommendations Approved
Is Key decision?: No
As part of the
normal process of service delivery, the approved highways capital
programme now requires amendments to allow effective delivery the
Programme.
Head of Service is asked to approve the reallocation of
residual funds from a completed project at Calder Vale to an
ongoing project in the Trough of Bowland.
Request details:
Transfer £50,000
From
Completed project: ID 17035 26/27 Calder Vale Road -
Barnacre-with-Bonds - Adjacent to 1-2 Victoria Terrace
To
In progress project: ID 17034 26/27 Sykes Farm Retaining Wall
32995 and Blaze Moss Culvert.
The reallocation is between projects in the same programme
and there is no change to the total approved budget.
The changes are required because additional work is required
to complete essential works at Sykes Farm and Blaze
Moss.
This item does not require cabinet approval.
Christopher Wilding
Bridges and Geotechnical Design Manager
6th October 2026
Enda Garvey, Interim Head of Highways Operations and Design has taken a decision to approve the proposed amendments to the Highways, Bridges Maintenance Capital Programme.
Divisions Affected: Longridge with Bowland;
Contact: Enda Garvey Email: enda.garvey@lancashire.gov.uk.
Date of decision: 06/10/2026