Decision Maker: Director of Highways and Transport
Decision status: Recommendations Approved
Is Key decision?: No
Head of Service
is asked to approve the reallocation of residual funds from a
completed project at Calder Vale and Grindleton to an ongoing
project in the Trough of Bowland.
Request details:
1. Transfer £42,000 from completed project ID 17035
26/27 Calder Vale Road - Barnacre-with-Bonds - Adjacent to 1-2
Victoria Terrace to in progress project: ID 17034 26/27 Sykes Farm
Retaining Wall 32995 and Blaze Moss Culvert.
2. Transfer £16,500 from completed project ID 17032
26/27 Grindleton Bridge 1072 to in progress project: ID 17034 26/27
Sykes Farm Retaining Wall 32995 and Blaze Moss
Culvert.
The reallocation is between projects in the same programme
and there is no change to the total approved budget.
The changes are required because additional work is required
to complete essential works at Sykes Farm and Blaze Moss and this
project now requires additional funds.
This item does not require cabinet approval.
Christopher Wilding
Bridges and Geotechnical Design Manager
20th October 2026
Enda Garvey, Interim Head of Highways and Operations has taken a decision to approve Changes to the Bridges Maintenance Capital programme October 2026.
Divisions Affected: Longridge with Bowland;
Contact: Enda Garvey Email: enda.garvey@lancashire.gov.uk.
Date of decision: 20/10/2026
Accompanying Documents: