Issue details

S278 Lytham Road Warton - Additional Funds

As part of S278 works the highway alignment at the junction of A584 Lytham Road and Church Road Warton was modified. Due to unforeseen circumstances additional works were required and as a result of this additional money is required from the developer to complete payments to the contractor.

Decision type: Non-key - Low

Decision status: Recommendations Approved

Divisions affected: Fylde South;

Notice of proposed decision first published: 08/01/2025

Anticipated restriction: Part I  -

Decision due: 7 Jan 2025 by Director of Highways and Transport

Lead director: Director of Highways and Transport

Department: Highways and Transport

Contact: Ridwan Musa Email: ridwan.musa@lancashire.gov.uk.