Decision Maker: Executive Scrutiny Committee
Is Key decision?: No
The purpose of this report is to provide a
summary of key performance of the Preston, South Ribble and
Lancashire City Deal Programme during and up to 2015/16 (Year 2).
In headline terms, early progress has been encouraging and by Year
2 a total of 1,599 homes have been delivered against a target of
1,206.
This report provides an overview of how the City Deal Programme has
performed during and up to 2015/16 (Year 2), highlighting progress
against targets. This information is also used to report to
Government progress towards agreed targets and notes progress up to
March 2016.
The Committee considered a report on the key performance against agreed targets of the Preston, South Ribble and Lancashire City Deal during and up to the end of 2015/16 (Year 2).
The Committee welcomed the considerable progress on highways infrastructure projects and on the housing completions. It was noted that none of the reported variances would affect the overall forecast over the City Deal period as they represented profiling changes only.
Resolved: That the recommendation set out in the report to Cabinet be noted, and that no additional comments or suggested alternative recommendations be made.
Divisions Affected: (All Divisions);
Contact: Eddie Sutton Email: eddie.sutton@lancashire.gov.uk Tel: 01772 535171.
Report author: Eddie Sutton
Date of decision: 12/07/2016
Decided at meeting: 12/07/2016 - Executive Scrutiny Committee