Decision Maker: Executive Scrutiny Committee, Cabinet
Is Key decision?: No
The purpose of this report is to provide a
summary of key performance of the Preston, South Ribble and
Lancashire City Deal Programme during and up to 2015/16 (Year 2).
In headline terms, early progress has been encouraging and by Year
2 a total of 1,599 homes have been delivered against a target of
1,206.
This report provides an overview of how the City Deal Programme has
performed during and up to 2015/16 (Year 2), highlighting progress
against targets. This information is also used to report to
Government progress towards agreed targets and notes progress up to
March 2016.
Cabinet received a report providing a summary of key performance of the Preston, South Ribble and Lancashire City Deal Programme during and up to 2015/16 (Year 2).
In presenting the report, the Leader highlighted some key achievements:
· £9.161m Private Sector investment leveraged
· 9,665sq m commercial floor space made available
· 753 jobs created
· 1,599 new homes built, with 8,675 having received planning permission
Resolved: That the progress being made on delivering the Preston, South Ribble and Lancashire City Deal Programme as set out in the report be noted.
Divisions Affected: (All Divisions);
Contact: Eddie Sutton Email: eddie.sutton@lancashire.gov.uk Tel: 01772 535171.
Report author: Eddie Sutton
Date of decision: 14/07/2016
Decided at meeting: 14/07/2016 - Cabinet