Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
The report sets out recommendations relating to a funding contribution from the County Council's Capital Programme to support the delivery of the proposed Phase 1 Extension to the existing Lomeshaye Industrial Estate.
This is deemed to be a Key Decision and the provisions of Standing Order No. 25 have been complied with.
The Cabinet approved the recommendations as set out in the full report.
Reason Key: Expenditure > £1,500,000;
Contact: Kathryn Molloy Email: kathryn.molloy@lancashire.gov.uk Tel: 01772 538790.
Date of decision: 09/11/2017
Effective from: 15/11/2017