Capital Strategy for Schools 2017/18 to 2019/20

Meeting: 10/08/2017 - Cabinet (Item 13)

13 Capital Strategy for Schools 2017/18 to 2019/20 pdf icon PDF 93 KB

:

Additional documents:

Minutes:

Cabinet considered a report on the schools capital grant allocation for 2017/18 to 2019/20, and the proposed strategy for expenditure, based on the priorities contained within the School Place Provision Strategy 2017/18 to 2019/20.

 

It was reported that, following publication of the report, two additional projects had been identified requiring urgent funding allocations in order to address immediate condition related remedial works, and it was proposed that the Schools Condition allocation proposals, as set out in the report, be amended to reflect the position as follows.

 

SCHOOLS CONDITION ALLOCATION

 

CONDITION FUNDING AVAILABLE

£000

 

 

Condition Allocation 2016/17

11,209

Condition Allocation 2017/18

10,956

 

Total available   

 

22,165

 

 

PROPOSED USE OF AVAILABLE CONDITION FUNDING

 

 

 

Approval to a condition led capital investment programme of £15.950m was given in the report to the Cabinet Member for Children, Young People and Schools on the 5th April 2017.  It was proposed to adjust the phasing of the allocation as follows:

 

 

 

Strategic maintenance of the building stock Priority 1 projects at community and VC schools to be delivered in  2017/18 (previously approved in Cabinet Report dated 5 April 2017 as part of the £15.950m  to have been delivered in 2017/18)

10,000

 

 

Further Phase: Strategic maintenance of the building stock plus £5.950m balance of Priority 1 projects (see above) at community and voluntary controlled (VC) schools, both to be delivered in 2018/19

10,040

 

 

Ongoing dry rot remedial works at Colne Lord St PS

1,500

Ongoing dry rot remedial works at Heasandford PS

505

Ongoing dry rot remedial works at Peel Park PS

120

 

 

Total proposed use

22,165

 

 

 

 

Resolved: That,

 

  i.  the proposed expenditure priorities for 2017/18 to 2019/20, as set out at  Appendix 'A' of the report, as amended, be approved.

 

  ii.  further reports be presented on individual project costs, any further  in-year allocations of capital funding and any adjustments to the three year programme as required.

 

  iii.  the inclusion of additional funding be authorised from individual schools into the respective capital project which, in turn, should be added to the capital programme and reported quarterly within the "Money Matters" report.

 

  iv.  the change in phasing of the condition programme be acknowledged.

 

  v.  additional funding of £0.505m, from the Schools Condition allocation for 2017/18, be provided to carry out dry rot remedial works at Heasandford Primary School Burnley.

 

  vi.  additional funding of £0.120m from the Schools Condition allocation for 2017/18, be provided to carry out dry rot remedial works at Peel Park Primary School, Accrington.

: