Cabinet considered a report setting out proposals for cycling, walking and environmental enhancements along the existing A6 Garstang Road, Broughton, in accordance with the planning conditions for the Broughton Bypass. The measures proposed in the report included new cycle tracks and the removal of an existing cycle track.

 

Resolved: That the construction and removal of cycle tracks as detailed in the report be approved.

: