The purpose of this report is to provide a
summary of key performance of the Preston, South Ribble and
Lancashire City Deal Programme during and up to 2015/16 (Year 2).
In headline terms, early progress has been encouraging and by Year
2 a total of 1,599 homes have been delivered against a target of
1,206.
This report provides an overview of how the City Deal Programme has
performed during and up to 2015/16 (Year 2), highlighting progress
against targets. This information is also used to report to
Government progress towards agreed targets and notes progress up to
March 2016.
Decision type: Non-key
Decision status: Recommendations Approved (subject to call-in by Scrutiny)
Divisions affected: (All Divisions);
Decision due: 12 Jul 2016 by Executive Scrutiny Committee
Decision due: 14 Jul 2016 by Cabinet
Contact: Eddie Sutton Email: eddie.sutton@lancashire.gov.uk Tel: 01772 535171.