Cuerden Strategic Site-Lancashire Central

This report provides Cabinet with a cost plan to secure the de-commissioning of the Lancashire Central (Cuerden Strategic Site) following the suspension of works on site by the county council after the announcement in May 2018 by IKEA that it no longer intended to occupy a plot on the site.

Decision type: Key

Reason Key: Expenditure > £1,500,000;

Decision status: Recommendations Approved

Divisions affected: Moss Side & Farington;

Notice of proposed decision first published: 09/08/2018

Anticipated restriction: Part II  - View reasons

Explanation of anticipated restriction:
The report contains commercially confidential financial information relating to the site works completed to date.

Decision due: 9 Aug 2018 by Cabinet