This report provides Cabinet with a cost plan to secure the de-commissioning of the Lancashire Central (Cuerden Strategic Site) following the suspension of works on site by the county council after the announcement in May 2018 by IKEA that it no longer intended to occupy a plot on the site.
Decision type: Key
Reason Key: Expenditure > £1,500,000;
Decision status: Recommendations Approved
Divisions affected: Moss Side & Farington;
Notice of proposed decision first published: 09/08/2018
Anticipated restriction: Part II - View reasons
Explanation of anticipated restriction:
The report contains commercially confidential financial information relating to the site works completed to date.
Decision due: 9 Aug 2018 by Cabinet
Lead member: Cabinet Member for Economic Development, Environment and Planning
Contact: Chris Dyson Email: chris.dyson@lancashire.gov.uk Tel: 01772 536641, Stephen Young Email: Stephen.young@lancashire.gov.uk Tel: 01772 536260.