Strengthening flood risk management and preparedness - Cabinet member responses to the recommendations of the scrutiny task and finish group

Meeting: 31/07/2020 - External Scrutiny Committee (Item 6)

6 Strengthening flood risk management and preparedness - Cabinet member responses to the recommendations of the scrutiny task and finish group pdf icon PDF 137 KB

:

Additional documents:

Minutes:

The Chair welcomed County Councillor Albert Atkinson, Cabinet Member for Technical Services, Rural Affairs and Waste Management; Rachel Crompton, Flood Risk Manager; John Davies, Head of Service Highways; and Marcus Leigh, Highways Service Manager – Infrastructure; to the meeting to present the written responses to the committee's recommendations on strengthening flood risk management and preparedness.

 

County Councillor Albert Atkinson, Cabinet Member for Technical Services, Rural Affairs and Waste Management, thanked the committee and the members of Strengthening Flood Risk Management and Preparedness Task and Finish Group for their comprehensive report. The recommendations of the task group had been looked at in great detail and the Cabinet Member accepted all of the recommendations. Timescales for proposed actions were also set out in the response.

 

A number of comments and issues were raised by members in relation to the written responses and the following was noted:

 

·  Assurance was sought by the committee that the ongoing review of staffing levels within the Flood Risk Management Team, would not result in a reduction in the number of staff supporting the function.

It was reported that following a recent restructure of the Highways Management Service a review of where the Flood Risk Management Team needed strengthening was currently underway. In addition a new manager post had been created within the team. Councillors suggested this information be communicated to Flood Action Groups to quash local rumour.

·  The acceptance of the cabinet member to create a culvert policy was welcomed by the committee. The importance of locating historic culverts was highlighted. In addition it was felt that a map identifying locations of riparian responsibilities across the county would be advantageous.

·  On surface water attenuation for new highways sponsored by the county council, it was reported that plans for current projects had already been completed and work was underway. It was pointed out that if the county council discovered aspects that could alleviate flooding then the appropriate action would be taken.

·  On concerns regarding riparian owners' responsibilities it was explained that the subject matter was felt to be of a technical /specialist nature that provided a barrier to some owners in understanding their responsibilities. It was reported that the county council was exploring new ways of explaining riparian responsibilities to residents and local landowners.

·  It was acknowledged that all risk management authorities were working within the constraints of a fragmented system. One member of the task and finish group had hoped that its work would have identified measures to reduce risk, improve resilience, speed recovery and build a single voice to influence change at a national level and felt that the outcome of the work was letters rather than leadership. In addition the member felt that they were unable to report back to their residents on what had changed as a result of the work undertaken. Furthermore it was felt that the county council did not recognise the value of flood action groups and the expertise they had and felt that the response to medium term recommendation M8  ...  view the full minutes text for item 6

: