The delivery of a scheme of road capacity improvements to the A582 South Ribble Western Corridor was identified in the Highways and Transport Masterplan for Central Lancashire in 2013. The county council is scheme promotor as Local Transport Authority and the scheme has formed part of the original delivery programme under the Preston, South Ribble and Lancashire City Deal since 2013.
This report presents the latest updates on the scheme and seeks approval for the submission of an outline business case to the Department for Transport for a focussed scheme and associated funding arrangements.
This is deemed to be a Key Decision and the requirements of Standing Order C19 have been complied with.
Decision type: Key
Decision status: Recommendations Approved
Divisions affected: Lostock Hall & Bamber Bridge; Moss Side & Farington; Penwortham East & Walton-le-Dale; Penwortham West; Preston Central West;
Notice of proposed decision first published: 10/01/2024
Anticipated restriction: Part I -
Decision due: 7 Mar 2024 by Cabinet
Lead member: Cabinet Member for Economic Development and Growth
Lead director: Executive Director of Growth, Environment & Transport
Department: Growth and Regeneration
Contact: Marcus Hudson Email: marcus.hudson@lancashire.gov.uk Tel: 01772 530696.